Nadeau Site, Hagar Township
Preserve the Dunes, Dec.18, 1997 |
MDEQ, Feb 10, 1998 |
Preserve the Dunes Feb. 18, 1998 May 15 Revisions
in RED |
Application to mine the Taube Road Extension in Hagar Township was made under the 1994 Sand Dune Mining Statute. Section 63702 of the statute allows mining in a Critical Dune Area only if (a)the operator had been mining the site prior to July 1989 or (b)the operator had been mining or permitted
to mine an adjacent property in a Critical Dune Area and prior to July 1989
owned the property for which the amended permit is being sought. The law
prohibits new mining operations in Critical Dune Areas. The Taube Road Extension
includes land in a Critical Dune Area. The Nadeau Site is not in a Critical
Dune Area. Therefore the Extension is a new mining operation in a Critical
Dune Area. Section 63702 does not allow an operator to come from an area
outside the Critical Dune Area and by amendment begin mining in a Critical
Dune Area.
Therefore, the permit was issued in error and should be revoked. |
Section 63702 of Part 637, Sand Dune Mining, of the Natural Resources
and Environmental Protection Act, 1994 PA 451, as amended (NREPA) does state
"the department shall not issue a sand dune mining permit within a
critical dune area"; however, the statute continues with the language,
"except under either of the following circumstances."
Please remember one of the basic principles the Department of Environmental
Quality (DEQ) utilizes in the enforcement of Part 637 of the NREPA. When
a permit is issued to a sand dune mining operator the permit covers all
of the contiguous acreage owned or leased by the operator. This position
of issuing only one permit on contiguous property extends to when an operator
acquires or leases additional property after the original permit is issued.
The issuance of the permit on all contiguous property is done to be consistent
with the intent of the original 1978 legislation of "limiting disturbance"
within designated sand dune areas. By issuing only one permit for all contiguous
acreage the mining company is limited to three active cell units at any
one time, TechniSand (formerly Manley Brothers of Indiana) purchased the
property that constitutes the Taube Road Extension from two private individuals
in 1981. Then in 1985 TechniSand purchased the existing permitted site,
the Nadeau Site, from the Unimin Corporation. When this second acquisition
occurred TechniSand had one option, to seek an amendment to the existing
permit for the Nadeau Site. Both of the transactions occurred prior to July
5, 1989 when the Critical Dune amendments became effective and; therefore,
provided TechniSand the exemption under Section 63702(1)(b). |
Our position and interpretation of the law remains unchanged. We have
consulted with one of the drafters of this section and it is his recollection
that the intent was to not allow an operator to extend from a non-critical
dune area into an adjacent critical dune area. The DEQ has chosen to interpret
the statute differently. The courts may have to decide whether one can begin
strip mining a virgin critical dune because one has been permitted to mine
adjacent land that is not in a critical dune.
Regarding the specifics of the GSD response, we have a copy of the Warranty
Deed dated July 31, 1991 by which TechniSand, Inc. bought the Nadeau Site
from Manley Bros. of Indiana, Inc. TechniSand acquired the land two years
after the July 5, 1989 effective date for the critical dune legislation.
Condition (b) of 324.63702 allows expansion in a critical dune area when
"the operator holds a permit issued pursuant to section 63704 and is
seeking to amend the mining permit to include land that is adjacent to the
property the operator is permitted to mine, and prior to July 5, 1989 the
operator owned the land or owned the rights to mine dune sand in the land
for which the operator seeks an amended permit."
This is a limited right to expand sand mining - limited to land owned
by the operator prior to July 5, 1989. TechniSand, the operator, did not
own the land prior to the effective date of the statute and hence cannot
amend its permit to include a critical dune.
For both or either of these reasons the permit was issued in error and
should be revoked. |
Nadeau Pit, Covert Township
Preserve the Dunes,Dec.18, 1997 |
MDEQ, Feb 10, 1998 |
Preserve the Dunes Feb. 18, 1998 May
15 Revisions in RED |
In summary, the engineering report notes the following violations of
the conditions of the permit for sand dune mining issued by the Geological
Survey Division of the M/DEQ.
1. More than 3 cells are active
The enclosed aerial photograph overlaid with the cell boundaries indicates
that 10 of 11 cells can be considered active. Only cell 1 has been reclaimed. |
1. "More than 3 cells active."
We have examined the aerial photograph and overlay that you provided
with your letter and find the following problems with your determination
that 10 of the 11 cell units at this site are active. Your aerial photo
is taken at an oblique angle which elongates the scale from north to south.
The cell unit configuration you used is not correct. On January 14, 1998,
TechniSand had the site flown by an aerial photography firm with proper
flight controls and then prepared an overlay which depicts the current topography,
vegetation, roads, buildings, etc. We have utilized this aerial photo and
conducted an on-site inspection and verified the current site conditions
as:
- Active Cell Units - Cell Units 6, 7, and 9
- Interim Cell Units - Cell Unit 3
- Released Cell Units - Cell Units 1, 2, 4, and 5
- Not Active - Cell Units 8, 10, 11, and 12 (west side of Blue Star Hwy.)
|
1. More than 3 cells are active
The memo states that "The cell unit configuration you used is not
correct." The boundaries were taken from information provided to us
by the DEQ in response to a FOIA request, TechniSand's
drawing incorporated in their PCUMRP latest revision November 1993. After two more requests we were provided with Amendments 5 and 6 to the permit which modified the Cell Unit boundaries.
We also requested under the FOIA a copy of the
map and overlay prepared by TechniSand. While our photograph did not have
ground controls it is generally correct. We have reviewed the map and overlay.
For the most part, it confirms our original findings as described below.
We understand that the PCUMRP was amended to create a "Plant Area"
for use in washing and storing sand. Otherwise, a cell is in one of four
states.
- Inactive: Untouched
- Interim Status: A cell has been mined and all mining activity has been
completed. It has been graded to slope not exceeding 1:3. It has been revegetated
per the PCUMRP and is in the first year of growth. Vegetation must have
taken root to cover 80% of the areas disturbed by sand mining and no single
area exposed to the elements is greater than 25 square feet. All mining
equipment has been removed except a roadway, conveyor or slurry pipeline
may be maintained and considered part of the plant site.
- Fully reclaimed or "released" (from conformance bond): The
plant material has sustained itself for one year. There are no areas where
the survival rate is less than 80% in any 10' x 10'.
- Active: Any cell not in one of the classifications above (other than
as part of the plant site), but generally, a cell unit being mined or used
for mining activity.
Through aerial photographs and an onsite inspection we have made the
following observations.
- Cell 1 has mining extraction and processing equipment stored in the
southwest corner. (See photograph on page 11.) The
eastern portion of the cell had been underwater. That portion is no longer
under water and is raw sand. Therefore, it must be considered active.
-
- Cell 2 was revegetated with grass along the west slope. A road runs
through the cell. By amendment part of the cell was added to Plant Area.
The eastern portion of the cell had been underwater. That portion is no
longer under water and is raw sand. Therefore, it must be considered active.
Though years have passed since the grass was planted, still no trees and
shrubs have yet been planted.
- Cell 3 was graded, revegetated and placed in interim status according
to the DEQ. However, the northern portion was being mined in November 1997.
See photo on next page. The vegetation has taken root on much less than
80% of the land disturbed by mining and there are large areas of bare sand.
Furthermore, the slopes at the edge of the water are greater than 1:3.
Therefore, it must be considered active.
- Disturbed areas in Cell 4 were left under-water or added by amendment
to the plant area. The eastern portion is no longer underwater, but is
exposed sand. Therefore, it must be considered active.
- Cell 5 may be similar to 4 or it was released in error since at least
an acre is raw sand. In addition the slopes at the edge of the water are
greater than 1:3. Therefore, it must be considered active.
- Cell 6 is active per DEQ.
- Cell 7 is active per DEQ.
- Cell 8 has bare exposed sand in the north eastern portion. Therefore,
it must be considered active. Furthermore, it has
a haul road through it which is prohibited by Special Condition 4 of the
permit.
- Cell 9 is active per DEQ.
- Cell 10 is not active. However, an onsite visit
indicates that a road has been used to move tracked vehicles to and from
the active mining areas in Cell 9 from Cell 11 in violation of Special
Condition 4.
- Cell 11 is active. Top soil has been stripped
from areas. An onsite visit indicates that a road has been used to move
tracked vehicles to and from the active mining areas in Cell 9. If not
active, this is a violation of Special Condition 4. See
page 11, item 2.
|
| 2. There are no interim cells. Reclamation was started on cell 2. However,
part of the cell that was underwater is now exposed raw sand with no reclamation
efforts. The enclosed table indicates the acreage of each cell and the portion
of each stripped of vegetation and portions reclaimed. These areas were
measured from the site plan prepared by Manley Bros. and laid over the aerial
photograph. |
2. "There are no interim cells."
There is one cell unit at this site in interim Status. Cell Unit 3 was
placed in Interim Status on May 27, 1997. The cell unit was mined, regraded,
and planted as of the site inspection conducted on March 4, 1997. The cell
unit will remain fully bonded until such time it is released. |
2. There are no interim cells. Cell Unit 3 was being mined early November
when our first aerial photophaphs were made. See the closeup of that activity
below. We have also confirmed that grading and revegetation of the cell
have not been completed. It is still in active status since it does not
meet the criteria for interim status.
 |
| 3. The one reclaimed cell is being used for unpermitted activities. Rather
than park vehicles in the Plant Area, they are being parked in reclaimed
portions of cell 1. |
3. "The one reclaimed cell is being used for unpermitted activities."
We conducted a site inspection and could not find any area within Cell
Unit 1 that is being utilized for parking cars. Since the aerial photo you
have utilized does not depict an accurate boundary for the cell units it
is possible the vehicles you believe are being parked within Cell Unit 1
are actually within the designated plant area. |
3. We agree that there are no vehicles parked in the reclaimed area of Cell
Unit 1. Per our eMail of January 30 we stated that what we had originally
thought were vehicles is actually abandoned equipment. The discussion under
"Additional Comments" on page
11 documents this and consequently our conclusion is accurate: The one
reclaimed cell is being used for unpermitted activities. |
| 4. Top soil is not being stockpiled and spread over reclaimed areas as stated
in the Progressive Cell Unit Mining and Reclamation Plan. |
4. "Topsoil is not being stockpiled and spread over reclaimed areas.
We disagree with your statement. There is currently topsoil stockpiled
in the east end of Cell Unit 6 and the south-west portion of Cell Unit 7.
These topsoil stockpile areas are evident on both the aerial photo which
you have utilized and the aerial photo flown on January 14, 1998. There
have been many topsoil stockpiles created and then utilized for reclamation
over the life of this mining operation, which is exactly what the Progressive
Cell Unit Mining and Reclamation Plan (PCUMRP) requires. |
4. The "top soil" in the east end of Cell Unit 6 is simply a pile
of fine brown sand. A search of the south-west portion of Cell Unit 7, revealed
no stockpiled top soil. |
5. Reclamation is not being completed in conformance with the amended
Progressive Cell Unit Mining and Reclamation Plan of 1989.
Grasses were used to revegetate portions of cell 2 instead of oaks, beeches
and other indigenous trees as proposed in the original cell unit mining
and reclamation plan, and instead of pine and poplar trees as proposed in
the 1989 amendment. |
5. "Reclamation is not being completed in conformance with the amended
Progressive Cell Unit Mining and Reclamation Plan of 1989."
The PCUMRP does not prohibit the use of other types of plant material
in the stabilization and revegetation of disturbed areas. Grasses are essential
to the success of woody vegetation and should not be planted at the same
time. The ideal method to ensure the survival of the woody species is to
first stabilize the disturbed area with grasses and then come back and plant
the trees and shrubs later. This is exactly what the operator is doing at
this site. |
5. Our observation stands that reclamation is not being completed in conformance
with the amended Progressive Cell Unit Mining and Reclamation Plan of 1989.
Cell Unit 2 has been classified "released" for a number of years.
Yet, the slope has had only a few trees planted at the very top of the slope.
It is still just a grassy slope. By releasing it, the DEQ has said that
it is fully reclaimed. It is not. |
6. The site has not been secured with a fence. Only small portions of the
site perimeter are fenced. |
6. "The site has not been secured with a fence,"
Special permit condition No. 1 does state, "The permittee shall
install and maintain fencing... in a manner restricting pedestrian access
...." this special permit condition does not mean the entire mining
operation should be fenced. We require the operator to install sufficient
fencing It and signs to achieve the intent of the permit condition, which
is to restrict pedestrian access. The permit condition addresses two concerns:
one to provide for public safety and two to prevent disturbance of reclaimed
areas. The operator at this site has installed sufficient fencing and signs
to deter pedestrian access to the site. |
6. Fencing and signage is inadequate to restrict pedestrian and off road
vehicle access. The property line at the Blue Star Highway has under 1,000
feet of fencing. This leaves about 4,400 feet open. Signage is sporadic.
At the south side of the north gate, there is a space wide enough to drive
a car through. There is no sign at or near the gate. This clearly not adequate.
Furthermore Special Permit Condition Nº 3 requires that the operator
prevent access by off road vehicles (ORV's). There is evidence of regular,
repeated access being made by ORV's. (See the photograph on the left of
a road where the dune has been eaten away by trucks and ORV's trying to
scale the side of a steep dune in Cell 10. Also see the photograph of the
ORV on top of one of the stripped dunes in Cell 9.) About 100 feet of fence
was added the week of April 6.
 |
7. The response to my Freedom of Information Act request indicates that
no up to date 15 year mining plan fulfilling the requirements of Section
63707 is on file. |
7. "No up to date 15 year mining plan."
The 15 year mining plan required by Section 63709 of Part 837 of the
NREPA is language from the original statute, enacted by the legislature
in 1976. The 15 year mining plan requirement is directed at a mining company
and is intended to depict the company's plans for mining on all of their
properties. If a company only operates one mining site then the 15 year
mining plan does only address one mining site. However, the reason for requiring
the 15 year, mining plan was so the DEQ will know what sites are being mined
and what sites may be mined in the future, i.e. where applications for new
permits may be requested. The law does not require any updating of a company's
15 year mining plan. |
7. Section 63704 states "(2)Prior to receiving a permit from the
department, a person or operator shall submit all of the following: ....
(d) A 15-year mining plan as prescribed by Section 63707." This means
that with each permit application, a 15-year mining plan must be submitted.
It would seem obvious that a plan for the next 15 years is required - not
one for some 15 years in the past.
Furthermore, not requiring an updated plan is unreasonable. A permit
is originally issued only after public hearings. One of the issues addressed
in an environmental impact statement is the amount of truck traffic, noise
and activity that is expected. It was estimated in 1978 that 400,000 tons
of sand per year would be mined at the Nadeau Pit. If the operator is now
removing 1,000,000 tons in a year this would be a very significant increase
and worsens the environmental impact. It effects life safety. It effects
the wear and tear on roads. It effects the quality of life by increasing
the noise level. The GSD is derelict in its duty to the taxpayers and citizens
of the state by failing to manage the level of activity at a sand dune mine.
Therefore, we maintain there is no up to date 15 year mining plan fulfilling
the requirements of Section 63707. |
8. The response to my Freedom of Information Act request indicates there
is no current Part 301 Permit on file with the Land and Water Management
Division. According to information provided by that Division, the last permit
was issued in 1990 and lapsed in 1993, 4 years ago. |
8. "No current Part 301 Permit on file."
Part 301, Inland Lakes and Streams of the NREPA is administered by the
DEQ's, Land and Water Management Division (LWMD). You are correct the Inland
Lakes and Streams permit did lapse in 1993. However, the permit has not
been renewed in part because of a shortage of staff in the LWMD. The company
has submitted a request for renewal of their Part 301 permit to the LWMD
which is pending. Usually normal operations are allowed to continue during
the permit renewal process, as long as the company operates in compliance
with the previous permit Conditions. |
8. The company has been operating without a permit for four years. The permit application was not filed until January 27,
1998. This is six weeks after we notified the DEQ and by copy, TechniSand.
Shortage of staff in the LWMD has had nothing to do with any delay so far
in securing a permit. This is not a usual situation. Allowing dredging operations
to continue when a permit is not in effect makes a mockery of the law. It
also indicates how little importance TechniSand places on compliance with
the law. By allowing the permit to lapse, TechniSand has opened the permit
up for a complete reassessment, which is very necessary to ensure that Rogers
Creek and the ground water supply to adjoining properties are protected.
Dredging should be halted until a full and detailed review of the permit
application has been completed. |
9. According to the Van Buren Conservation District a duplicate copy of
the 15 year mining plan is not on file per 63707(2). |
9. "A duplicate copy of the 15 year mining plan is not on file,
with the VanBuren Conservation District, per 63707(2)."
The 15 year mining plan for this site was prepared and submitted by the
original Manley Brothers of Indiana in February 1978. A public hearing on
the "Intent to Issue a Permit" was held on February 20, 1979 at
the Berrien County Courthouse. It is the practice of the Department to make
available all documents prepared by the applicants for a permit at several
locations including the local area prior to the public hearing. The Notice
of Public Hearing indicates we did make the documents available at the County
Clerk's office for VanBuren County from February 8, 1979 to March 9, 1979.
We would have provided the same information to all other interested agencies,
including the Soil Conservation Districts, at that time. Our records do
not verify, by specific correspondence, that we did send the documents to
the VanBuren County Soil Conservation District; therefore you may be correct
in this allegation. |
9. No further comment, except that it is the responsibility
of the sand dune mine operator, not the DEQ, to file with the Conservation
District. |
Additional Comments, Nadeau Pit
Preserve the Dunes, Jan 30, 1998 |
MDEQ, Feb 10, 1998 |
Preserve the Dunes Feb. 18, 1998 May 15 Revisions
in RED |
1. We have been informed that sand has been brought in from other mines
for washing at the Nadeau Pit. This has never been mentioned in any permit
applications to the Geological Survey Division or to the Land and Water
Management Division. The operation increases the demands for ground water.
This additional use of ground water was never analyzed in the environmental
impact study. Nor were the impacts of additional truck traffic addressed.
Futhermore, processing of sand from other sites is against the zoning ordinance
of Covert Township. This practice should be stopped or the permitting process
should be reopened to consider the impacts of these operations. Public hearings
need to be held before these operations are included in the sand dune mining
permit. |
1. "Sand has been brought in from other mines for washing at the
Nadeau Pit."
Sand is not being brought into the Nadeau Pit from an off-site source
and then processed utilizing the wash plant at this site. In order to process
sand from an off-site source the company would need a means to off load
the sand from trucks, place the sand on a conveyor system, and then introduce
the sand into the wash operation through the slurry pipeline system. There
are no facilities at this site to accommodate this type of activity.
However, a sand dune mining operation that provides sand for the foundry
industry must create a final product which meets the specifications of the
customer. There are very few sand mining operations that are able to produce
a final product for their customer without blending sands from other sources.
Therefore, bringing sand from other sources is both a common practice and
an essential practice to the sand dune mining companies which produce foundry
sand. A sand dune permit issued under Part 637 of the NREPA regulates the
mining and reclamation of sand from the site under permit, it does not regulate
the processing of other sands which is necessary to create a saleable product.
The blending of sand from off-site sources is not a violation of the law
or the permit. The processing of the additional sand brought in from off-site
sources does not increase the demands for ground water. The wash operation
at this site utilizes water totally contained within the boundaries of the
mining site. The wash operation is not consumptive, the water is recirculated
and remains on site. |
1. Sand has been brought in from other mines for processing at Nadeau
Pit. We base this statement on a copy of a letter from John Crow attorney
for TechniSand, Inc. to Harold Schuitmaker attorney for Covert Township,
dated June 1,1995 in which he states "this is to advise that TechniSand,
Inc. has its processing plant in Section 36, between Blue Star Memorial
Highway and I-196, and for years has been hauling sand from other sites
in Covert Township to that site for processing."
The permit process and the related documents for this sand dune mine
never contemplated converting the site to a processing plant for sand brought
in from other mines. No public hearings were held regarding such a change.
These activities represent significant change in the impact of mining activity
on neighboring properties, state roads, and persons living along the truck
route to and from the site. Furthermore, it is against the zoning ordinance
of Covert Township as was confirmed by Harold Schuitmaker in his written
response to Mr. Crow.
In addition to the above concerns regarding Nadeau Pit, the permit application
for the "Nadeau Site Taube Road Extension" indicates that
sand will be conveyed by truck to the Nadeau Pit for washing and processing.
This would be a serious and significant change in the operations at the
Nadeau Pit. Before such change in use is made, the EIS should be revised
and public hearings held. |
2. Should cells 10 and 11 not be considered active, because the mined area
is minor and was mined in error or unintentionally, TechniSand is then in
violation of Special Permit Conditions, Item 4, since both cells are being
used to move equipment fundamental to the mining operation. |
2. "Should Cells 10 and 11 not be considered active.
Our on site inspection and our evaluation of the January 14, 1998 aerial
photo does not indicate any activity within Cell Units 10 and 11. These
cell units are not active. |
2. The reply was non-responsive. The cells are
being used to move equipment fundamental to the mining operation. See the
photo of road below.
 |
3. Last year an additional entry has from the Blue Star Highway has been
added north of the original one. This change in the use of the site has
been made without revision to the cell unit mining and reclamation plan.
This exposes more neighboring properties to noise, dust, disturbance and
hazards of heavy truck traffic. This item was omitted in the December letter. |
3. "Additional entry from Blue Star Highway."
You are correct the company did not make a formal request to amend their
permit by adding the second access road into the north end of the site.
However, the company did request approval to re-open this access point in
a letter dated, March 11, 1997 and on April 10, 1997 the DEQ did respond
and provided approval for the use of this second haul road access As this
action was an improvement to a previously existing road, we did not regard
this request to be significant enough to warrant a formal amendment to the
permit. |
3. The new entry has not been open since the first permit was issued in
1978. It was not just a reopening but a change in the use of the site and
represents more than a minor change. It is further evidence of the lack
of control and management that the DEQ exercises in the performance of its
responsibilities to the people of Michigan. |
| 4. Item 3 in our original letter indicated that vehicles were being parked
in Cell1, the only cell that has been reclaimed. This was an error. Actually,
what we had thought were vehicles are abandoned pieces of mining equipment.
I believe the violation is the same. |
4. "Abandoned pieces of mining equipment in Cell 1"
On inspections of the site no abandoned mining equipment has been observed
in Cell Unit 1 |
4. Our inspection found the equipment pictured below within Cell Unit
1. These are very large and evident pieces of junk. An aerial photograph
pinpoints the location.
A later aerial photograph taken in early April
indicates that the equipment was relocated into the plant area and the adjacent
portion of Cell Unit 1. |
Busse Property, Covert Township
Preserve the Dunes, Dec.18, 1997 |
MDEQ, Feb 10, 1998 |
Preserve the Dunes Feb. 18, 1998 May 15 Revisions
in RED |
1. The last amendment was issued to expand the mining operation
onto adjacent land owned by Glover Dandridge. In applying for the amendment
TechniSand made several misrepresentations, or at least misleading statements.
The application letter dated May 3, 1994 states "TechniSand, Inc.
has recently secured an agreement with the landowners, and proprietors of
the Blue Star Lounge, ...." The agreement is actually dated July 15,
1994.
They further state "The area to be amended includes 1.02 acres which
is owned by Glover Dandridge and Adella Bracken of Covert, Michigan and
1.06 acres which is owned by TechniSand, Inc. The addition of this acreage
to Cell 4 will increase the active acreage in Cell 4 from 7.16 acres to
9.24 acres." While the facts are generally true they misled the Division
to state on the permit that the Cell was increased to 9.24 acres. In fact,
the original permit indicated that the area of Cell 4 was 8.08 acres. The
additional area from the adjacent property, assuming 50 foot buffer area
is 2.12 acres as drawn (2.33 acres per the conditions of the purchase agreement).
Therefore, the area of Cell 4 is actually between 10.20 and 10.41 acres
- exceeding the largest cell permitted by law.
Without comment the amendment application letter states that there will
be a 50 foot wide buffer around the perimeter of the pit. The buffer at
the south end of the pit had been 100 feet. Section 63706 at the time of
the permit amendment (September 15, 1994), required a 200 foot deep buffer
area unless the Department determined that the sand mining activity was
compatible with the adjacent existing land use. The property directly south
of the expanded pit is zoned R-1, single family residence and clearly is
not a compatible use. No exception in the buffer width should have been
made. |
1. "The area of Cell 4 is actually between 10.20 and 10.41
acres - exceeding the largest cell permitted by law."
We believe you have misinterpreted the information provided by TechniSand
in their May 3, 1994 letter requesting an amendment to the size of Cell
Unit 4. The request by TechniSand indicated the area to be amended to Cell
Unit 4 included 1.02 acres owned by Glover Dandridge and Adelia Bracken
and 1.06 acres owned by TechniSand. The 1.06 acres owned by TechniSand is
already included in the 8.08 acres identified as the current acreage for
Cell Unit 4. Therefore, the revised acreage for Cell Unit 4 is now 9. 10
acres (8.08 acres + 1.02 acres), which does not exceed the ten-acre limit
provided by law.
The 200' buffer does not apply to this cell unit because the site was
permitted and the cell unit was active prior to the 1994 amendments to the
statute which added the 200' setback requirements. |
1. No we did not misunderstand. You failed to understand the game
of semantics that TechniSand played.
They stated "The area to be amended includes 1.02 acres which is
owned by Glover Dandridge and Adella Bracken of Covert, Michigan and 1.06
acres which is owned by TechniSand, Inc. The addition of this acreage to
Cell 4 will increase the active acreage in Cell 4 from 7.16 acres to 9.24
acres." The statute does not govern the active area of a cell unit,
but the total area. While the facts are generally true they misled the Division
to state on the permit that the Cell was increased to 9.24 acres. The original
permit indicated that the area of Cell 4 was 8.08 acres. The additional
area from the adjacent property is not 1.02 acres. Including the 50 foot
buffer the area is 2.12 acres as drawn on the revised PCUMRP or 2.33 acres
based on the conditions stipulated in the sand purchase agreement. Therefore,
the area of Cell 4 is actually 10.41acres - exceeding the largest cell permitted
by law.
The date of the permit was September 19, 1994. The amendments changing
the setback requirements were made immediately effective on May 24, 1994
and the relevant DEQ regulations became effective June 24, 1994. Furthermore,
TechiSand did not even have the right to mine the sand until its sand purchase
agreement was executed on July 15, 1994, 22 days after the amended regulations
became effective. No exception in the buffer width should have been made.
Furthermore, in the original permit the set backs were 100' except along
the Blue Star Highway. This amendment reduced the setbacks to 50' without
even notification to adjacent property owners. |
2. Reclamation has not been made in accordance with the 1986 amended Progressive
Cell Unit Mining and Reclamation Plan. Reclamation was to be a continual
process. Top soil was to be removed and spread on to areas where mining
had been completed. Trees were to be planted on the stabilized slopes. |
2. "Reclamation has not been made in accordance with the 1986 amended
Progressive Cell Unit Mining and Reclamation Plan."
Reclamation has been an ongoing process for many years. The company completed
the last of the regrading in Cell Unit 4 in the fall of 1997 and should
complete the remaining vegetative planting in the spring of 1998. |
2. Our first concern is that the practices used
in the Nadeau Pit will be followed here. Cell Unit 2 at Nadeau Pit was planted
with grass years ago, placed in reclaimed status, conformance bonds were
released, and still today trees and shrubs have not been planted.
The PCUMRP described a process of continual reclamation. As mining was
complete in an area, it would be regraded and planted. We now have an entire
cell that is raw sand. Reclamation has not been made in accordance with
the 1986 amended Progressive Cell Unit Mining and Reclamation Plan.
In late March, Cell Unit 4 was hydroseeded without
topsoil being spread over the raw sand. By mid-May an onsite inspection
revealed that only 10% of the seed germinated. |

|
3. The response to my Freedom of Information Act request indicates that
no up to date 15 year mining plan fulfilling the requirements of Section
63707 is on file. |
3. "No up to date 15 year mining plan fulfilling the requirements
of Section 63707 is on file.
The 15 year mining plan which is required by Section 63707 of Part 637
of the NREPA is language from the original statute that was enacted by the
legislature in 1976. The 15 year mining plan requirement is directed at
a mining company and is intended to depict the companies plans for mining
all of their properties. If a company only operates one mining site then
the 15 year mining p]an does only address one mining site. However, the
reason for requiring the 15 year mining plan was so the DEQ will know what
sites are being mined and what sites may be mined in the future, i.e. where
applications far new permits may be requested. The law does not require
any updating of a company's 15 year mining plan. |
3. See our comments above regarding the 15 year mining plan for Nadeau Pit.
No up to date 15 year mining plan fulfilling the requirements of Section
63707 is on file. |
4. The site is not and has not been fenced. |
4. "The site has not been fenced."
Special permit condition No. 1 does state, "The permittee shall
install and maintain fencing.... in a manner restricting pedestrian access
...." We do not enforce this special permit condition as meaning the
entire mining operation should be fenced. We require the operator to install
sufficient fencing and signs to achieve the intent of the permit condition,
which is to restrict pedestrian access. The permit condition is to achieve
two purposes: one to provide for public safety and two to prevent disturbance
of revegetated areas which have been reclaimed The operator at this site
has installed sufficient fencing and signs to deter pedestrian access to
the site. |
4. During mining there was little to no fencing. Even though the danger
to pedestrians has passed, it is still necessary to protect the reclaimed
areas before they enter interim status. Fencing is needed. There is clear
and obvious evidence of ORV's driving over the graded slopes on the site.
The site was used for hunting earlier in the year. It is possible to walk
or drive an ORV from the parking lot of the Blue Star Lounge right into
Cell Unit 4. An on site inspection indicates that the fencing is anything
but adequate to protect the reclamation efforts when they are made and to
restrict pedestrian access. |
5. According to the Van Buren Conservation District a duplicate copy of
the 15 year mining plan is not on file per 63707(2). |
5. "A duplicate copy of the 15 year mining plan is not on file per
63707(2).
The 15 year mining plan for this site was prepared and submitted by the
original Manley Brothers of Indiana in February 1978. A public hearing on
the "Intent to Issue a Permit" was held on February 20, 1978 at
the Berrien County Courthouse. It is the practice of the Department to make
available all documents prepared by the applicants for a permit at several
locations including the local area prior to the public hearing. The Notice
of Public Hearing indicates that we did make the documents available at
the County Clerk's office for VanBuren County from February 8, 1979 to March
9, 1979. We would have provided the same information to all other interested
agencies, including the Soil Conservation Districts, at that time. Our records
do not verify, by specific correspondence, that we did send the documents
to the VanBuren County Soil Conservation District, therefore, you may be
correct in this allegation. |
5. No further comment, except that it is the responsibility of the sand
dune mine operator, not the DEQ, to file with the Conservation District. |