Preserve the Dunes

TechniSand given Dredging Permit

The DEQ issued a permit to continue dredging at the Nadeau Pit. We have been told that the base line against which impairment is measured is from current conditions forward. Thus, the fact that the Rogers Creek's base flow has been seriously reduced and that what had been described as a first class trout stream when dredging first began no longer has any fish in it cannot be considered. The falacy of this reasoning is obvious. The mining company assures the regulators that there will be no adverse impacts on the stream; but there are; but there won't be anymore; but there are; but .....

TechniSand Seeks New Dredging Permit

Twenty-three days before their dredging permit for Nadeau Pit in Covert Township was to expire, TechniSand applied for a new one. Within three days the MDEQ issued a public notice. This allowed the required 20 days for public comment before the existing permit expired. Many neighbors were not notified because the application did not include a complete list of adjacent property owners.

PTD's review of the permit application indicated that there were numerous omissions and errors in the application. The application "estimates" that they will dredge 260,000 cubic yards of sand (350,000 tons or 13,000 truck movements) and enlarge the lake to 36 acres. PTD is concerned about potential harm to nearby Rogers Creek, a natural trout stream, the water quality of the lake when dredging is complete, and the impact on reclaimed slopes. Protections that were included in the expiring permit have been ignored.

Our comments have been communicated to the MDEQ. We also requested a public hearing, as did Thunder Mountain Heights Land Corporation and Covert Township. The hearing was held Wednesday, May 19, 2004 at the Covert Township Hall.

No permit had been issued by September 1, however the DEQ has stated that prior damage to the creek from earlier permits cannot be taken into consideration now.

 

Michigan Supreme Court Rules

The Michigan Supreme Court issued its opinion on August 31, 2004. The court ruled 4-3, along party lines, that PTD's claim that the permit was illegally issued was filed too late, and that the Michigan Environmental Protection Act (MEPA) could not be used to challenge a permit. Unbelievably, they drew a parallel between a permit that was challenged because it did not dot all the "i" 's and cross all the "t" 's and our challenge that the permit was issued in direct conflict with the law. They then justified their ruling on the basis that businesses would cease to invest in Michigan if a permit could be questioned after 60 days of being issued. Because they ruled that we were time barred, the judges did not have to rule on the legality of the permit. No on/e has ever ruled that the permit was legally issued, not the trial judge, the Court of Appeals, nor the Supreme Court.

The three judges in the minority issued a strongly dissenting opinion that supported the ruling of the Court of Appeals ruling and our position that the permit was illegally issued and should be rescinded.

The Court of Appeals will now review the remaining issues in the case. The most important issue is what standard should be used to determined if the proposed removal of the dunes in the critical dune area represents the destruction of natural resources. Our claim that it does is based in part on the finding of the Legislature that

"The critical dune areas of this state are a unique, irreplaceable, and fragile resource that provide significant recreational, economic, scientific, geological, scenic, botanical, educational, agricultural, and ecological benefits to the people of this state and to people from other states and countries who visit this resource. "

and

"The benefits derived from alteration, industrial, residential, commercial, agricultural, silvicultural, and the recreational use of critical dune areas shall occur only when the protection of the environment and the ecology of the critical dune areas for the benefit of the present and future generations is assured."

The order of the Supreme Court has attracted attention of the press in the state. In an editorial the Detroit Free Press pointed out that in our case and that of "National Wildlife Federation v Cleveland Cliffs," the court was preventing citizens from effecting enforcement of environmental protections.

Subsequent Activities

TechniSand filed a motion with the Court of Appeals to dissolve the injunction that prohibited mining within the critical dune area at the Nadeau Site Expansion. PTD filed a brief in opposition. On September 2, the court of appeals denied TechniSand's motion.

Preserve the Dunes has requested that new briefs be filed on the remaining issues and that oral arguments be heard since the initial briefing and oral arguments had focused on the legality of the permit. We are awaiting a response from the court.

The Michigan Court of Appeals ruled in favor of Preserve the Dunes, Inc. in its lawsuit against Michigan Department of Environmental Quality and TechniSand, Inc.

The ruling prohibits mining of the critical dune areas at the Nadeau Site in Hagar Township. PTD filed the suit in July 1988. After receiving an unfavorable ruling in Berrien County Trial Court in December 2001. PTD appealed the ruling. Arguments were heard in April, 2002 and the court issued its 26 page ruling October 4, 2002. The ruling is "published," which means that it can be used by attorneys in other cases as a basis for interpreting the law. About 1 in 10 decisions are "published."

For more details see the April newsletter, the Herald-Palladium article, or the South-Bend Tribune article. See the Herald-Palladium editiorial from October 9 for a discussion of the importance of this ruling.

 

Court Grants Motion for Temporary Injunction

The court issued a temporary injunction stopping all mining activity in the critical dune area of the Nadeau Site. Unfortunately, TechniSand will be allowed to remove sand from the site that they had moved to their "plant area" outside the critical dunes. They will also be able to mine the parts of the site that are outside the critical dunes. We are elated and hopeful that this ruling indicates that the court will rule in our favor and protect these dunes from destruction just as every other critical dune area is protected by the law. We still wonder how the DEQ rationalized the granting of a permit for mining these dunes. Read the press release for more information.

PTD Renews Motion for Temporary Injunction

After waiting four months and documenting that TechniSand has cleared and removed a significant portion of one of the critical dunes at Nadeau Site, we filed on August 22, 2002 a motion for a temporary injunction to stop further disturbance of these dunes. Read the brief.

PTD Argues Case in Court of Appeals

Phil Neal presented the oral arguments before the Court of Appeals. PTD members who were present all agreed that our arguments were convincing and those put forward by the DEQ and TechniSand were clearly "bogus." We hoped for a ruling in a very short time.

PTD Files Motions with Court of Appeals

Once Hagar capitulated PTD filed a motion with the court of appeals for an injunction to stop mining of the critical dune area of the Nadeau Site until our appeal is heard and a decision rendered. We cited irrecoverable harm to the dune area -- they will be removed. In a separate motion we also asked for an immediate hearing of the case. We await the court's response.

Hagar Township Folds in Mediation

Hagar Township and TechniSand entered in to court ordered mediation. In the face of TechniSand's threats of demanding over $20,000,000 in damages, the township negotiators were bullied into an agreement -- a bad one at that. See the January 2002 newsletter (2,400K) for detailed coverage and analysis of the agreement. Or sign-up at the guest book and we will mail you a copy.

TechniSand Sues Hagar

TechniSand has sued Hagar Township alleging that by refusing to change the zoning of the Nadeau Site so that they can apply for a mining permit the township has "taken" their property. They are asking the court to award them damages of $21,000 per day and direct the township to allow the mining.

DEQ extends Nadeau Pit permit.

Despite the protests of citizens (over 85 showed up for the hearing) the DEQ renewed TechniSand's permit to mine at the Nadeau Pit. Some additional restrictions were placed on the operation at the request of Preserve the Dunes. We had hoped for more -- but the DEQ is not willing to strictly enforce these environmental protection laws under the current administration. Most disappointing was that the extension was for five years thus shutting out meaningful review and input by citizens.

Hearing on Sand Dune Mining Permit Renewal

The DEQ held a public hearing on TechniSand's application for renewal of the sand dune mining permit for the Nadeau Pit in Covert. The hearing was February 26. We were pleased that State Representative Mary Ann Middaugh (Van Buren County) attended. In total, over 80 persons attended the hearing. All who spoke were opposed to renewal of the permit. PTD comments centered around violations ­ violations that we believe justify revocation of the permit. These comments were also submitted in written form are are available through the link above.

Hearings on Rezoning in Hagar Township

A public Hearing on TechniSand's application for a rezoning of the "Nadeau Property" from Residential-Agricultural to Commercial or Industrial was held January 2. Their request was denied. They subsequently came back on February 13 with a request to change the zoning to R-2. This would have allowed lots as small as 1/3 acre. Their request was denied again. TechniSand is not interested in developing this land. They want to strip mine it. If the land were to be rezoned, TechniSand will then be able to apply for a sand mining permit under the Hagar Township Mineral Removal Ordinance. The Hagar Township Board confirmed the actions of the Planning Commission. TechniSand's only option is to try to get the courts to over rule the township.

Appeal Brief Filed

In March Preserve the Dunes filed its brief for the appeal on the lower courts ruling. This brief contains a clear statement and analysis of the law governing sand dune mining in critical dune areas. We recommend it for your reading. Phil Neal (Neal, Gerber & Eisenberg of Chicago) took the lead in preparing it with assistance from our trial lawyers Tom Fette (Taglia, Fette, Dumke, Passaro & Kahne of St. Joseph) and Jeff Haynes (Beier Howlett of Bloomfield Hills).

Judge Rules

On November 30, 2000 five months after he promised and three weeks after the election, Judge Maloney ruled -- against Preserve the Dunes. Charles Davis, President of PTD, commented "They won, we lost. We'll appeal. We will prevail." A press release (PDF) was issued by PTD on December 1 outlining some of our concerns regarding this ruling. The judge ruled that no single dune formation within the critical dune areas was protected, only the entire assemblage of critical dunes. Following this logic, only the last critical dune will be protected. In his ruling he states that this will be the last critical dune area to be mined. He should have noted that this is the first new mine in a critical dune area to be mined since the sand dune mining law was amended to prohibit mining of critical dunes. A copy of the ruling (24 pages) is available both as a web page (you will need Netscape 6.0 or Internet Explorer 5.0 to view it) and in Adobe Acrobat format.

TechniSand delays application for permits to mine the Knauf Property.

The proposed mine was discussed in the August newsletter and analyzed in depth in our comments submitted to the DEQ at the hearing. The public hearing for the permit is reported below. We expect the mining company to submit a modified application in a few months. It will respond to information requests from the DEQ, including the hydrogeology of the area, area of fill in the wetlands needed to build an access road, and access rights across the Ross Preserve. PTD will have its engineers, hydrogeologists and attorneys review their submissions to ensure that they are complete and correct. More detailed information is available in the October newsletter.

Dereliction of Duty -- a number of environmental groups from across the state, including Preserve the Dunes, issued a joint report on the failure of the DEQ to protect the environment and natural resources of Michigan. The report covers sand dune mining; ground water contamination; refusal to protect Humbug Marsh, the largest and most significant coastal wetland on the Detroit River; dioxin contamination near Midland; PCB pollution in the Crotty Street Channel near the Saginaw River; refusal to regulate concentrated animal feeding operations; and more.

New Sand Dune Mine Proposed -- A public hearing was held on TechniSand's application for a sand dune mining permit on August 22, 2000 at the Covert Township Hall. Over 125 citizens attended. 31 spoke in opposition to the mine. No one spoke in favor. This site is surrounded on three sides by Ross Preserve. Besides destroying a beautiful dune area, it threatens to destroy wetlands both on and off the site. An overview of the permit and the likely side effects, if the permit is issued, is presented in the August newsletter. The DEQ is taking the matter into consideration and has 90 days in which to make its decision. We are waiting with anticipation and concern.

TechniSand's Poor Performance Record -- In response to queries from a number of sources we have posted this listing of TechniSand's record of violations and poor reclamation practices in its mines in Covert and Hagar Townships.

Trial Status -- We are still waiting for the judge's decision on our suit to prevent the opening of a new sand dune mine within a Critical Dune Area in Hagar Township. The final arguments were made May 12 in Berrien County Trial Court before Judge Maloney on May 12, 2000. On May 3rd each side submitted its Proposed Findings of Fact and Conclusions of Law. A summary of the facts presented at the trial is included in a recent newsletter or check out the link above to read the legal document.

The trial date for the lawsuit against the DEQ and TechniSand was March 14-17, 2000, and March 21-22, 2000. This legal action is being taken to stop a virgin critical dune in Hagar Township from being stripped mined for sand. The mine is commonly referred to as the Nadeau Site. A press release/advisory gave background for the trial.

In response to the Lake Michigan Federation's publication "Vanishing Lake Michigan Sand Dunes: Threats from Mining" the Department of Environmental Quality issued a press released that we think was misleading. We have responded point by point. An Adobe Acrobat version of their press release and our response is available here.

NEWS ON THE LAWSUIT

We are still waiting Judge Maloney's decision. The trial was held March 14 through March 23, 2000. Proposed Findings of Fact and Conclusions of Law were submitted on May 3. The oral arguments were heard by Judge Paul Maloney in the Berrien County Courthouse on Friday, May 12.

The Court of Appeals declined to hear our appeal on December 10, 1999 on the basis that there is no reason the appeal cannot be heard after the final ruling in the case is made. We must therefore wait until the final ruling is entered before appealing the May 24, 1999 ruling.

On August 5, 1999, Preserve the Dunes had filed an appeal of the judge's ruling made at the hearing on May 24, 1999 was filed. The text of the appeal can be downloaded in Adobe Acrobat® format.

Preserve the Dunes had filed a motion for summary disposition of its complaint against the MDEQ and TechniSand on March 19, 1999. It is supported by a brief that spells out why the court should have declared the permit to mine in critical dunes invalid, rescinded the permit and enjoined TechniSand from mining or removing sand from the critical dunes area at the Nadeau Site.

************

In parallel with the suit, we have been monitoring activities at several mines and notifying the DEQ, our legislators and local government officials of existing and new violations. One ongoing issue has been the DEQ's unlawful change of the boundaries of mining cells at the Nadeau Pit.

************

Preserve the Dunes sues the MDEQ and TechniSand. The Press Release summarizes the complaint that was filed on July 2, 1998. On August 7, 1998 the complaint was amended to clarify its basis under the Michigan Environmental Protection Act.

TechniSand and the MDEQ file for dismissal of our complaint and a change of venue. A hearing was set for October 26, 1998. TechniSand then requested that discovery should be delayed until after the hearing.

On September 14, Judge Peterson denied TechniSand's requested to delay discovery.

October 16, Tom Fette, attorney for Preserve the Dunes, filed his brief in opposition to the motions of TechniSand and the MDEQ. On October 26, the Judge denied TechiSand's and the MDEQ's motions for dismissal and change of venue.

************

In June, 1998 we wrote to Russ Harding, Director of the Michigan Department of Environmental Quality (MDEQ), in response to his letter assuring us that all of the violations that we documented would be addressed.

After several investigations by members of Preserve the Dunes, Inc. during October 1997 we retained an engineering firm to review the mining activities at the Nadeau Pit and the application for extending the mine at Nadeau Site- Taube Road Extension. Click here to review the report.

Our first action was to notify the MDEQ of violations at two mines operated by TechniSand, Inc., a division of a large multinational corporation, Fairmount Minerals, Ltd. and to question issuing of permit to extend one mine into a Critical Dune Area.

In December 1997 we wrote to Michael Cote, Supervisor of the Plainwell District for the Geological Survey Division of the MDEQ, and to Les Thomas who heads up Permit Consolidation for the Land and Water Management Division of the MDEQ.

The MDEQ finally responded in February but simply "stonewalled" the issues that we raised. Eight days later we rebutted their response and presented a comparison of our allegations, the MDEQ reply and our responses. In early May the attorney generals office promised that the MDEQ would respond in detail to all of our observations. In early June, Russ Harding promised a detailed response after the investigation was complete. The full summary of correspondence can be found here (988K in Adobe Acrobat 11 x 17" format).

Since these letters were sent we have met with some of our State Representatives (James M. Middaugh, 80th District & Charles LaSata, 79th District) and State Senator Harry Gast to brief them on our concerns. We presented a number of issues that are outlined in three one page documents:

© Preserve the Dunes, Inc.
P.O. Box 581, Riverside, MI 49084
Write us Write us